Our Projects 

Explore our work within the Government and Private sectors as QRSE Builders strives to provide Quality Results through Skillful Execution. 

CT-37740 ABC

Cesspool to Septic

Makalei Residence Septic Design-Build

Performed the site assessment, percolation test, and design to obtain permits, executed the construction of the new septic system, and closed out the old cesspool. Designed and installed the 1250-gal septic tank with an associated leach field and backfilled the existing cesspool.  A pump was added due to the discovery of a secondary sewer source lower than the installed septic intake. A cost evaluation was conducted to compare adding a pump to the secondary sewer line versus lowering the septic system and intake, since the construction of the system had already started, and adding the pump proved to be the most economical solution. 

Aina Momona Cesspool Closure and Assessment

Conducted a site survey and performed an alternative wastewater solution assessment, confirming existing composting toilets have replaced the use of an existing large-capacity cesspool. Currently awaiting permit approvals to complete the cesspool closure and EPA notification.

Zane Residence Septic Design-Build

Designed and installed a 1500-gal septic tank with associated leach field to replace the previously abandoned cesspool found to be active and in need of emergency repair and replacement. Performed site assessment, percolation test, and design to immediately execute construction and close out the cesspool with after the fact permitting because of the emergency scenario found with the existing cesspool having been filled by a previous contractor with debris while still active.  After backfilling the septic system, restoration of landscaping was also performed.

ASB Cesspool Closure & Assessment

QRSE conducted a site survey and alternative wastewater solution assessment and confirmed connection to the county sewer system.  Cesspool closure executed and final conditions filed and cleared with EPA.

 A Cesspool Assessment for the ASB Hanapepe Branch performed by others identified one (1) operable cesspool located on the property, 6 ft diameter, 8 ft 6 in depth. QRSE checked as-built plans from the County Wastewater Division to design a proposed lateral connection and based on a plan and profile of a sewer line along the Kona Road address of the bank, a section of the CoK wastewater Plan & Profile drawing indicated that service to the existing sewer may have already been installed, but only showed the connection from the CoK sewer to the property line.

 A site visit revealed saw cuts and asphalt replacement in the parking lot, indicating work had been completed from the building, intersecting at the cesspool, and traveling to the Kona Road CoK sewer line.  QRSE coordinated an investigation that would show running water from the property to the sewer manhole #2 (SMH#2), with CoK observers.  A traffic control plan was prepared, and the permit was approved by CoK, to redirect traffic on Kona Street. SMH#2 was accessed, the property water was turned on, and flow was observed and confirmed by all in attendance at the lateral connection.  QRSE also checked that water from the property did not flow into the cesspool.

 The CoK Wastewater Division and Building Division – Building permits section accepted the QRSE findings without requiring any “after the fact” connection fees or permits be provided.

Renovations

Gerber Collision & Glass Office Renovation

Managed and constructed this project with a phased design and permitting approach to accomplish the interior demolition of the old jewelry store showroom and sales floor, and renovation to a new auto body shop and customer reception area with updated electrical wiring, lighting, and interior finishes.  The new auto body shop also included epoxy flooring for the training area, customer drive-in inspection area, and windshield installation work bay area.

Halawa Home Renovation

This home re-modeling project was to repair a wind and rain-damaged home apartment for a client as an insurance adjusted claim. The scope included replacing all the flooring, priming and painting all the internal walls, ceiling beams, trim and baseboards, and replacing all the doors and knobs. In the two bedrooms, replacing the closet doors, shelving, and rods. The bathroom included the vanity, quartz countertop and sink, full height cabinet, baseboards, and back splash. The kitchen included the countertop, sink, tile backsplash, and top and bottom cabinets. The carport included the ceiling, paint, and finish trim. Other exterior work included prime and painting facia, soffit and installation of rain gutters. We than needed to update all electrical and lighting including replacement of all outlets, fixtures, switches due to water damage, replacement of wall plates, rewiring of pinched wires, relocation of outlets and electrical for the kitchen, relocating cables, install lighting in the carport, adding outlets to removed extension cord in carport, and removal of abandoned electrical wires or meter as appropriate, including redwood wire mold.

New Construction

BSA Camp Pupukea New Pool Shower Building

This new pool shower building construction will include demolition of the old shower building and an existing cottage, new concrete foundation, concrete masonry walls, glulam roof trusses, metal roof & gutters, plumbing and electrical, and painted finishes, new septic and graywater systems, and new ADA ramp and parking lot.  Currently awaiting permit approvals to get started with work.

Hilo Combined Support Maintenance Shop (CSMS)

Our team was contracted by J & J Worldwide Services to provide Project Management, Contractor Quality Control (CQC), and on-site Safety services for the prime contractor, Alutiiq General Contractors, LLC.  This Hawaii Army National Guard new maintenance facility was approximately 90% complete and had been stalled due to delays and the loss of key personnel. We assessed the status of the initial punch list items and remaining work and restarted the subcontractors for HVAC, Building Controls, Plumbing, Fuel Station, Paint Booth, Concrete and Asphalt paving, Grading, and Landscaping.  We evaluated the partially performed and changed work scopes, negotiated and processed modifications to subcontractors, requested payment from the government for work completed, and then paid subcontractor invoices, some over 6 months due before they would return to work. Three additional subcontractors needed for the Fuel Station were not even contracted and had to be solicited, competed, and justified for selection by our Project Manager. We also restarted the CQC process assessing the status of previous submittals, identifying critical missing submittals still needing preparation, reviewing and documenting the quality of work in place, and developing RFI’s on issues found to be holding up work. These actions resulted in seven more contract modifications with the government, which they would not commit to for over 6 months due to lack of funding, further delaying the project.  To maintain progress, our CQC Manager also became the Project Superintendent, having established a rapport with all subcontractors during the CQC submittal and RFI processing, efficiently scheduling and sequencing multiple subcontractors, testing and inspections, documenting results, and reducing on-site staffing costs.  The Fuel Station proved to be a unique design that could not be easily satisfied by industry-standard equipment packages and required a concerted CQC effort managing designer, controls manufacturers, fuel system installer, electrical subcontractor, and a third-party commissioning agent.  A final inspection was held satisfactorily with the government a little over one year after QRSE took on this project.

Haleakala - Maui Space Surveillance Complex

QRSE was contracted by J & J Worldwide Services to support the prime contractor, Alutiiq General Contractors, LLC. with Contractor Quality Control (CQC) and site Safety & Health services. This Air Force contract being executed by the Honolulu Engineer District (HED) of the US Army Corps of Engineers (USACE) had been delayed due to redesigning the catwalks without welding to the maximum extent possible, with the resultant loss of key personnel. Within a month of the project restarting, QRSE was asked to fill these personnel voids.  This maintenance contract to replace existing steel catwalks that surround the three Ground-Based Electro-Optical Deep Space Surveillance (GEODSS) telescopes at the Maui Space Surveillance Complex (MSSC), was located at over 10,000 feet in elevation on the summit of Mt. Haleakala.  The high altitude and extreme weather of the site posed unique hazards, and rare environmental and cultural conditions to be addressed in performing the work of demolition and removal of existing steel catwalks and erection of new prefabricated steel catwalks. QRSE demonstrated our understanding, knowledge, and commitment to ensure compliance with these requirements during the project re-start and coordination meetings, using the USACE Resident Management System (RMS) for all records in a timely manner, gaining the confidence of both the HED project execution team and the on-site Airforce staff.  Our team, integrated with Alutiiq’s construction management team, performed and coordinated the three-phased CQC inspection process, safety management, and verified environmental protections within the production schedule, to ensure contract compliance and delivery of a quality product that satisfied users and HED quality assurance inspections. 

Have a Project in Mind?

Let’s Get Building!

Contact Us

2117 Saint Louis Drive, Honolulu, HI 96816

By appointment only

CT-37740 ABC